Trusted time and time again.
Livengood Excavators Inc. is trusted time and again to accomplish excavation needs that range from personal residential paving to large scale commercial development.
4539-4555 Freedom Way
Center Valley, PA
179 acre site, 10.8 mil project
Full line site work Infrastructure including:
- Erosion and sedimentation
- Earthmoving
- Sanitary sewer
- Storm sewer
- Waterlines
- Block curb
- Asphalt paving
- Bio and storm management basins
Cloverleaf Plaza
Rt. 100
Breinigsville, PA
Prepare site and infrastructure for a new hotel including:
- Erosion control
- Earthmoving
- Utility piping
- Asphalt paving
- Entrance roadway and HOP paving improvements
St. Lukes Medical Office Building
Lehighton Development Partners
Blakeslee Blvd., Lehighton, PA
Site work preparation for a new St. Lukes medical office building including:
- Clearing
- Erosion controls
- Earthmoving
- Utility piping
- Asphalt paving
Iron Hill Construction
3835 Green Pond Road
Bethlehem, PA
1.3 mil project
Prepare site and infrastructure including:
- Erosion and sedimentation controls
- Clearing
- Earthmoving
- Export fill
- Bio-retention basins
- Storm sewer
- Sanitary sewer
- Waterlines
- Concrete curbing
- Asphalt paving
3 Furnace Drive
Allentown, PA
4.5 mil project
Complete site re-development of Allentown's Lehigh River Front. Formerly an industrial site, the improvements included the site work, infrastructure and redevelopment of the entire site into modern apartments, commercial, retail, and class A office space. The redevelopment also involved upgrade of a new sanitary interceptor main, an amphitheater, and a new Riverwalk along the water’s edge.
Site preparation project including:
- Site erosion and sedimentation controls
- Earthmoving
- Rock excavation
- Blasting and crushing
- Storm sewer
- Sanitary sewer
- Water distribution
- Fire lines
- Curbing
- Asphalt paving
Blue Mt. Resort
1660 Blue Mountain Drive
Palmerton, PA
Waterpark, Summit & Valley Lodge Expansions, Employee parking
These projects included the re-alignment and construction of a new
access roadway and parking for the proposed waterpark, Site work improvements
for the Summit lodge, and Valley Lodge, along with employee parking.
Medical Office Building
Jaindl Land Development
1431 Nursery St
Fogelsville, PA
Prepare site for a 40,000 SF medical office building including:
- Erosion control
- Earthmoving
- Utilities
- Site and off-site paving
Traditions of America
2612 Union Ct.
Bethlehem, PA
122 acre site, 210 units for 55+ active adult community, 10.2 mil
Full line site work Infrastructure including:
- Clearing
- Complete erosion and sedimentation
- Earthmoving
- Storm management basins
- Storm sewer
- Sanitary sewer
- Waterlines
- Curbing
- Asphalt paving
- HOP Improvements
Giant Supermarket and Shopping Center
15100 Kutztown Rd., Ste. 3
Kutztown, PA
Cedar Properties
39 acre site, 88,000 SF building area, 5.9 mil
Prepare site for a New Giant Food market and shopping center including:
- Complete site Improvements
- Infrastructure
- HOP improvements
- Complete site erosion and sedimentation controls
- Earthmoving
- Storm sewer
- Sanitary sewer
- Bio-retention basins
- Water distribution
- Off-site water extension
- Curbing
- Asphalt paving
and Shopping Center
Weis Markets #188
Route 100, Glenlivet Dr.
Allentown, PA
15 acre site, 74,000 sf building pad, 4.8 mil
Site preparation project including:
- Site erosion and sedimentation controls
- Earthmoving
- Rock excavation
- Blasting and crushing
- Storm sewer
- Sanitary sewer
- Water distribution
- Fire lines
- Curbing
- Asphalt paving
Weis Markets #168
3825 Sullivan Trail
Easton, PA
11 acre site, 68,000 sf of building pads, 2.2 mil
Full line site work project including: Site erosion and sedimentation controls
- Earthmoving
- Storm sewer
- Sanitary sewer,
- Water distribution
- Fire lines
- Curbing
- Asphalt paving
- Widening of Sullivan Trail Rd.
- HOP paving improvements
PA Rt. 512 Realignment & Reconstruction
Jaindl Land Development
6996 Bath Pike
Bethlehem, PA
Complete site work inrastructure, earthmoving, utilities and paving for an Industrial, commercial, and business park. This work was concurrently performed along with the complete re-alignment, reconstruction, and new full depth paving replacement of Pa Rt. 512 and all HOP improvements including:
Site preparation project including:
- Site erosion and sedimentation controls
- Earthmoving
- Rock excavation
- Blasting and crushing
- Storm sewer
- Sanitary sewer
- Water distribution
- Fire lines
- Curbing
- Asphalt paving
Jaindl Land Development
151 Boulder Drive
Breinigsville, PA
A 400 acre industrial park involving the complete site work Infrastructure, earthmoving, utilities, and paving of all roadways. The scope of work also included construction of two bridges, and complete off site grading, utilities, and HOP paving Improvements.
200 Boulder Drive
Breinigsville, PA
Site preparation project including:
- Site erosion and sedimentation controls
- Earthmoving
- Rock excavation
- Blasting and crushing
- Storm sewer
- Sanitary sewer
- Water distribution
- Fire lines
- Curbing
- Asphalt paving
8001 Industial Blvd.
Trexlertown, PA
Site preparation for an 800,000 sf warehouse distribution center. Site work included 70 acres, for an 800,000 sf building pad including:
- Earthmoving
- Utilities
- Site concrete
- Asphalt paving
and The Landings
Jaindl Land Development
1224 Fritch Drive
Macungie, PA
Prepare site for 385 units of single family, twin, townhome, and apartments, and recreation areas including:
- Clearing
- Grubbing
- Erosion measures
- Earthmoving
- Utilities
- Asphalt paving
Jaindl Land Development
3672 Vista D
Macungie, PA
Complete site work infrastructure preparation for 400 units of single family, twins, and townhomes, along with extensive recreation areas including:
- Erosion measures
- Earthmoving
- Sanitary sewer
- Storm sewer
- Water utilities
Pulte Homes
22 Chandler Way
Orefield, PA
A residential development consisting of 320 units of single family, twins, and townhomes. Project included:
- Erosion control
- Earthmoving
- Utilities
- Curb, asphalt paving
- HOP Improvements
Over 400,000 cy of earth moved
(cold storage warehouse)
7132 Ruppsville Road
Allentown, PA
Prepare an 80 acre site, for a 1,000,000 sf cold storage facility including:
- Erosion control
- Earthmoving
- Storm sewer
- Utilities
Over 600,000 cy of earth was moved to prepare the building pad